aFRR and mFRR: Activation markets explained for industry

In the previous article we covered the fast frequency reserves FCR, FCR-N and FCR-D, which intervene within seconds to slow a frequency deviation. Those rese...

In the previous article we covered the fast frequency reserves FCR, FCR-N and FCR-D, which intervene within seconds to slow a frequency deviation. Those reserves stabilise the grid, but they do not bring it back into full balance. That last step is the job of the next two reserves in the sequence: aFRR and mFRR. They are called activation markets because the power here is not merely standing ready; it is actively called in when the system needs it.

This article explains what aFRR and mFRR are, the difference between automatic and manual activation, when a battery is a good fit, and how smaller units enter through aggregation. The aim is to give industrial decision-makers an accurate picture of the markets that a battery's flexibility is typically optimised against today.

From stabilisation to restoration

The fast reserves and the activation reserves solve two different jobs. FCR is the first response that stops the frequency from running too far from 50 hertz. aFRR and mFRR are the heavier reserves that then bring the frequency all the way back and free the fast reserves so they are ready for the next event. That principle is described in Energinet's Outlook for Ancillary Services, where aFRR and mFRR are referred to as the reserves that restore the balance once the fast reserves have stabilised it. Energinet is Denmark's national transmission system operator.

Together, aFRR and mFRR make up what in Danish are called frequency restoration reserves. The difference lies in how quickly and how they are activated.

Upregulation and downregulation

Two concepts recur across all activation markets. Upregulation means that more power is supplied to the grid, or that consumption is reduced, typically because the frequency has fallen below 50 hertz. Downregulation is the opposite: less generation or more consumption when the frequency is too high.

For a battery the link is concrete. When the battery discharges and delivers power to the grid, it contributes to upregulation. When it charges and draws power from the grid, it contributes to downregulation. Precisely because a battery can do both, it can in principle take part in both directions, but aFRR and mFRR are offered as asymmetric products, where a provider can bid up or down separately, as described in Energinet's Outlook for Ancillary Services 2024-2040.

aFRR: automatic restoration

aFRR, the automatic Frequency Restoration Reserve, is activated without human intervention. The unit continuously receives a signal from Energinet via the SCADA system and adjusts its power accordingly. According to Energinet's product overview for DK1 and DK2 (Denmark's two bidding zones, Western and Eastern Denmark), aFRR has a response time of five minutes, and the signal is sent every four seconds. So it is a reserve that is regulated finely and continuously, close to real time.

For the energy itself, aFRR is linked to the European market. Activated aFRR energy is traded through the common European platform PICASSO, which Energinet is connected to, and which ENTSO-E describes in more detail. That means Danish aFRR forms part of a larger European market rather than standing alone.

Demand for aFRR is rising. Energinet has revised the expected aFRR need upwards in both Western Denmark and Eastern Denmark, primarily because more solar and wind create more and faster imbalances that need to be regulated, cf. Energinet's Outlook for Ancillary Services 2024-2040. For an industrial reader the point is not the forecast figures themselves, but the direction: the fast, continuous regulation that batteries among other resources can deliver is becoming more in demand as generation becomes more variable.

mFRR: manual activation

mFRR, the manual Frequency Restoration Reserve, is instead activated by a decision in Energinet's control centre. When there is a need, Energinet sends an order to the relevant providers to up- or downregulate, as described in Energinet's tender conditions for system services. mFRR relieves the faster reserves during larger and longer-lasting imbalances.

Activation time is changing. Historically, mFRR had to be fully activated within 15 minutes, but with the automatic Nordic activation market introduced in 2025, the full activation time for the standard product has been reduced to 12.5 minutes, cf. Energinet's Outlook for Ancillary Services 2024-2040. The market itself, the automatic Nordic mFRR energy activation market, went live on 4 March 2025 and moved Nordic balancing from 60-minute manual to 15-minute automated settlement. The Nordic market is intended as a step on the way toward the common European mFRR platform MARI, which Energinet is helping to develop.

mFRR is also split into two stages that are worth knowing. Energinet first procures capacity in advance to ensure that sufficient reserve is available. A provider that is awarded capacity is then obliged to submit a matching bid in the energy activation market itself, where the energy is traded when it is called in. Capacity and energy are priced independently, and the provider is settled separately for the two parts. For an industrial business this is a technical detail, but it explains why participation in mFRR is about both making capacity available and actually being able to deliver the energy when the order comes.

The battery's role relative to heat and power

Batteries are not the only participants in the activation markets, and they are not equally strong in all of them. Their advantage is speed and precision: they can hit a setpoint quickly and repeatedly without start-up time. That makes them well suited to aFRR, where regulation is continuous and close to real time.

In mFRR, where the time window is longer, the picture is more mixed. Here thermal plant and electric boilers also play a significant role, and they can deliver large volumes of regulation over the longer periods that mFRR covers. A battery has a limited energy store and cannot readily hold full power for long stretches, whereas a heat plant or an electric boiler can regulate large energy volumes for as long as there is fuel or heat demand. The point is not that batteries displace heat and power plant in every reserve, but that each market has its own logic. The battery is strongest where response speed and precision weigh heaviest, and it supplements rather than replaces the slower resources in the heavier regulation tasks.

Aggregation: how smaller units enter

Most industrial batteries are individually too small to participate directly in the activation markets, which typically require a certain minimum size. The solution is aggregation. Several units are pooled in a portfolio that bids as a combined delivery, and balance responsibility for the whole sits with one party. The requirements for that kind of combined delivery form part of Energinet's tender conditions.

The framework for aggregation has also been strengthened. Since 1 January 2025, aggregator companies have a statutory right to access the electricity markets on non-discriminatory terms, cf. the executive order on aggregation. For an industrial business that means participation does not require the unit alone to meet the markets' size requirements. It can form part of a larger pool that a partner administers.

Where ZynexGroup stands

For us, aFRR and mFRR are the markets our optimisation model is primarily aimed at today. We handle the commercial optimisation of the installation through a partner that aggregates and bids the portfolio into the relevant markets. We are not ourselves the balance-responsible party on the customer's behalf, and we do not trade in the customer's name.

ZynexGroup finances, builds, owns and operates the battery. The host provides a little outdoor space and site rights and receives a monthly share of operating profit. That share depends on the market and operating results and is never guaranteed. Site-specific economics are confirmed in the assessment and proposal. Use the free battery calculator to assess space requirements. Battery export requires the grid company’s permission, and approval is not guaranteed.

ZynexGroup's approach to site assessment

We always assess the concrete installation and site before we talk market. Grid connection, consumption profile and the operating needs the business has determine what a battery can realistically contribute, and how much capacity may need to be reserved for other purposes such as backup power rather than market participation. On that basis we have a data-based conversation about what makes sense for that particular business.

Overall perspective

aFRR and mFRR are the reserves that restore the balance after the fast FCR reserves have stabilised the frequency. aFRR is activated automatically and continuously, while mFRR is activated manually by Energinet's control centre and now has a standard activation time of 12.5 minutes. Batteries are particularly well suited to the faster parts, but they enter a market where thermal plant and electric boilers also contribute, and where smaller units enter through aggregation.

ZynexGroup handles operation and market optimisation through a partner. The host’s monthly share of operating profit therefore depends on the market and operating results and is never guaranteed.

Have the potential for your site assessed

If you want to know what an industrial BESS installation can realistically contribute at your site, we start from your own data: grid connection, consumption profile and history. On that basis we produce an initial assessment of whether there is a match, and what the next step could then be. You are welcome to contact us.